The overhaul of the M-14 highway section is underway on the approach to Kherson

image

Avtostrada continues to restore the part of the road connecting Kherson with Nikolaev. Our site on the approach to Kherson has not been repaired for about 20 years, so before the start of work it was in poor condition.
Currently, a middle layer of asphalt concrete is laid on one side of the road along almost the entire length, and work is underway to install it on the other side. By the end of the road construction season, we plan to complete the laying of all layers, including the top of gravel-mastic asphalt concrete. After the overhaul, the total thickness of the base and three layers of coating will be more than 60 cm.
In parallel, the specialists of the company:

  • arrange congresses;
  • strengthen the roadside;
  • arrange a modern drainage system with rainwater and inspection wells. The water treatment system will provide water purification before entering the reservoir.

In the village of Chornobaivka we are starting to install modern LED lighting. Work is also underway on the bridge over the Verevchyna River.
More than 80 Avtostrada employees and about 50 units of equipment are involved in the works on the site. The Marini 3000 soil mixing plant and asphalt plant with a capacity of 260 tons per hour cover the need for materials.
The route M-14 "Odessa - Melitopol - Novoazovsk" is an important transport artery passing through the territory of Odessa, Mykolaiv, Kherson, Zaporizhia and Donetsk regions. The road is the part of the European route E58. Restoration of a site on the approach to Kherson will improve communication with Nikolaev that will have positive impact on development of economy of both regions.